Project Details
Location: Livonia, Michigan
 Owner: Ford Motor Company
 Delivery Method: Construction Commodity Management
 Project Value: $2,000,000
Architect/Engineer: SSOE
Size: 5,000 SF
 Size: 5,000 SF

Construction Commodity Manager

Stenco was the general contractor for the construction of a 5,000 SF Chiller Building addition to the cooling tower structural steel on the south side of the Ford Livonia Transmission Plant.
This nine month project consisted of:
- Piping work
 - Electrical grounding
 - Concrete foundations and asphalt paving
 - Structural steel fabrication and erection
 - Siding, roofing, and gutter work
 